CHC-logo.ashxCrafton Hills College, New Science Center, San Bernardino City USD. Budget: 18,000,000. Start Date: NTP -1 Issued 12/13/2013. NTP-2 Forecast for 01-26-2013. Project Completion 06-05-2015

Construction of new 34,147sf. Type II fully sprinklered Science Center. This Science Center includes a 2 story fully equipped laboratory wing along with a 2 story Lecture/ Faculty Wing. The two buildings are connected by an exterior walkway system.

This project presents several grading and site logistic challenges due to the building being located on the side of a hill. Grading will include backfilling of an existing canyon. Structure consists of structural steel with brace frames, concrete foundations, walls, and columns. Exterior includes Pre Cast Concrete panels, metal stud framing, and store front window systems. Site work includes new drainage system upgrade with storm water treatment vaults, settlement ponds, and rip rap.

no images were found

  • Skills : DSA Inspection, SBCUSD
  • Adam Price, DSA Inspector Class 1